Looking from the Commons into the Gallery
|
Janitor Closet
|
Coffee Room insulation and rough-in completed.
|
Kiln Room.
|
EPDM roofing at the Commons has been completed.
|
Curbs are finished at the Running Track
|
Roofing at the Locker Area and Library is 95% complete.
|
Curbs and retaining walls being built at the west side of campus.
|
Locker Room CMU ledge where the Metal Lockers will be installed.
|
Lifting one of the Skylight panels.
|
Taping Drywall at in a Tutorial Hallway.
|
Taped Tutorial Room.
|
Front Entry arches.
|
Lazy River a.k.a. the Running Track.
|
Locker Room bench supports installed.
|
Locker Room shower stall.
|
First Floor Classroom Corridor
|
Retaining wall at Stair #3 exit door.
|
Plaster lathe and scratch coat underway at the Second Floor.
|
Tutorial Corridor has received a prime paint coat.
|
Teachers Work Area is being drywalled.
|
Retaining wall at the Basketball Court
|
Back Entrance
|
Retaining walls and sidewalks are underway.
|
Athletic Field has been graded.
|
Ceiling grid and 1st finish coat of paint are in.
|
Gymnasium backboard supports are installed.
|
Gallery Skylight.
|
Work at the Athletic Field is underway.
|
Retaining walls and grading ongoing at the Basketball Court and Play Area.
|
Plaster work completed at the back of the skylight.
|
Stair exit door retaining walls and plaster work underway.
|
Plaster work near completion at the northwest elevation.
|
West elevation plaster work completed.
|
Gymnasium windows and doors are installed.
|
Parents Room
|
Girls Locker Room has been block-filled.
|
Library drywall underway.
|
Stage and Commons areas.
|
Main Entry with Copy Room above.
|
Administrative Corridor.
|
Lower Level bathroom tile work is underway.
|
Lower Level Tutorial Rooms, painted with ceiling grid being installed.
|
Stair 2
|
West Entry
|
Art Room cabinets being installed.
|
Teacher's Work Area
|
West side with Play Area retaining wall installed.
|
Looking south, plaster is being applied at the Second Floor exterior.
|
Entry brickwork is underway.
|