Roof Top Unit #2 being lifted and placed.
|
Roof Top Unit #2 being lifted and placed.
|
Roof Top Unit #2 in place.
|
Roof Top Unit #3 above the Commons.
|
Roof Top Unit #3 in place.
|
Block work at the Library.
|
Stair #3 steel installation is underway.
|
Storage Room at the north end of the Gymnasium.
|
Copy Room 225 above the Gallery.
|
Concrete being poured and finished in the Gallery Area.
|
The Gallery into Stairwell #1.
|
Roofing installation at the north portion of the Building.
|
The Gymnasium is prepped for the concrete slab pour.
|
Stair #2 at the Lower Level.
|
Duct and Steel Stud work at the west portion of the Second Floor.
|
EPDM Roofing is underway.
|
The Gymnasium concrete slab has been poured.
|
Looking south through the Locker Room area.
|
Plumbing and Electrical rough-in at the Servery.
|
Brick veneer is being installed at the west side of the Building.
|
Library roof trusses are installed.
|
Trusses and plumbing rough-in at the Locker Area
|
Looking east through the Gallery at the Main Entry
|
Trusses and metal decking at the Servery
|
Completed EPDM Roofing at the west side of the Main Building
|
EPDM roofing underway at the Gymnasium
|
Brick Veneer at the west side is nearing completion
|
Looking south at the completed sheathing, steel framing, wood gutterboards and shingled roof.
|