Mock-up of the tile layout for the Gallery
|
Stage & Commons drywall being finished.
|
Staking is completed at the Playground
|
Bathrooms at the First Floor being tiled.
|
Entry arches are nearing completion
|
Rolling Door at the Parents Room has been installed.
|
Lower Level Lobby.
|
Lower Level drinking fountain has been installed.
|
Plaster work continues at the Second Floor exterior.
|
Looking through the Gallery at the Main Entry
|
Tutorial Room magnetic white board installation in progress
|
Art Room Countertops, shelving and sink area.
|
Coffee Area
|
West side asphalt prep and fence post work.
|
Basketball court is ready for asphalt.
|
Field underdrainage installed.
|
Girls Locker Room
|
Library entrance casework is installed.
|
Lower Level Storage area corridor.
|
Tutorial Room
|
First Floor Classroom with magnetic whiteboards installed.
|
First Floor Bathroom tile work.
|
Bathroom countertops and sinks are installed.
|
Stage flooring and painting is underway.
|
Asphalt and markings completed at the northwest area near the playground.
|
Playground curb work is underway.
|
Fencing is being installed at the basketball court.
|
Concrete is being placed at the Main Entry.
|
Gymnasium painting is underway.
|
Gallery drywall taping and finishing is near completion.
|
Servery sinks and cabinets/countertops being installed.
|
Restroom fixtures have been installed.
|
First Floor Classroom corridor broadloom carpet has been installed.
|
Second Floor Transition Room closets.
|
Lower Level Stair 1 tile work.
|
Teachers Work Room.
|
Coffee area tile is installed.
|
Topsoil is being distributed.
|
Playground work is underway.
|
MODot and Main Entry areas are being paved.
|
Exterior Parking lights are being installed.
|
Wood panel installation at the Commons.
|
Painting at the Gallery.
|
First Floor Classroom corridor.
|
Lower Level doors and hardware are installed.
|
First Floor Administrative bathroom.
|
Wood frames and carpet at the Reception area.
|
Gymnasium joists, ductwork and basketball posts are being painted.
|
Artist tiles are being installed at Stair 1.
|
Second Floor Classroom corridor.
|
Second Floor Gallery area floor tile is complete.
|
Teachers work area is nearing completion.
|