Servery countertops and cabinets are installed.
|
Gallery tilework is ongoing.
|
Exterior B-ball hoops are in place.
|
Stair 1 tile work is nearing completion.
|
First Floor bathroom.
|
Second Floor Classroom Corridor
|
Second Floor at Stair 1.
|
Teacher food prep area
|
Admin area doors are installed
|
Trophy Case wood frame and lights are installed
|
Gymnasium painting is ongoing
|
Toilet partitions are installed at the Locker Rooms
|
Exterior lighting has been installed. Downspout installation is underway.
|
Playground underdrainage is complete.
|
First Floor Elevator corridor.
|
Commons and Stage ramp wood paneling is ongoing.
|
Commons cabinets and countertop are installed.
|
Stair 1 wood cap is installed.
|
Library entry & Trophy corridor tile underway.
|
Reception Entry
|
Gymnasium Entry vestibule.
|
Gymnasium floor and striping is near completion.
|
MODoT road work is near completion.
|
View from the road.
|
Pavers are being installed at the Main Entry.
|
Cornerstone
|
Time Capsule installed.
|
Placing the Cornerstone
|
Servery is near completion.
|
Reception desk is under construction
|
Library Corridor
|
Furniture is being installed in the Administrative wing.
|
Landscaping around the Detention Basin.
|
A view of the Commons from the stage.
|
Stair 1 Corian panels are underway.
|
Lower Level Tutorial listening devices are installed.
|
Plaster work is ongoing at Stair 1
|
Teacher’s Work Area systems furniture
|
Reception desk is being installed
|
Lower Level Storage Room
|
Teacher lunch area
|
Development Office furniture has been installed
|
First Floor Classroom projectors are installed
|
Asphalt and striping at the Running Track is complete
|
Fine grading is near completion and landscaping will begin shortly around the interior of the parking area
|
Landscaping continues around the perimeter of the parking lot
|