January

Page 1  |  Page 2
January
Steel Trusses installed for the Mansard Roof System.
January
Brick veneer underway at the east wall of the Gymnasium.
January
Looking South at the Exterior Steel Stud, Sheathing & Roof Truss installation.
January
Brick Veneer being installed at the Lower Level west wall.
January
Concrete is being pumped onto the 2nd Floor.
January
Framing in the windows at the Lower Level.
January
Gymnasium east wall brick veneer and stone coping are near completion.
January
West side of the Gymnasium and Commons brickwork.
January
Lower Level  Pipe and Ductwork
January
Lower Level Stairs being formed up for concrete.
January
Lower Level elevator shaft and piping.
January
Looking south over 2nd Floor West.
January
2nd Floor East framing and metal deck at the roof trusses.
January
2nd Floor Copy Room.
Library
Metal decking being installed at the roof trusses.
January
View of the east side of the Building.
January
Looking South at the Exterior Steel Stud, Sheathing & Roof Truss installation.
January
Brick veneer installation at the Lower Level and 1st Floors of the North West wing.
January
First Floor east ductwork.
January
First Floor west ductwork.
January
Looking south through the Gymnasium.
January
Underground plumbing work in progress.
January
Electrical conduit and panel boxes at the Commons.
January
2nd Floor Northeast Wing.
January
Metal decking is completed at the Roof.
January
Wood blocking at the Commons Roof for the RTU curb.
January
Skylight at the Gallery.
January
West side of Building.
January
Northwest brick veneer continues.
January
Looking South at the continuing Exterior Stud and Sheathing work.